| Sr No | Proposed Activities under WSHP | Total |
|---|
| 1 | Total Channels | 1649 |
| Proposed Channels | 106 |
| Completed Work Channels | 921 |
| In-progress Work Channels | 100 |
| Other Works Channels | 522 |
| 2 | Existing Water Bodies (ABY) | 52 |
| Proposed Water Bodies | 149 |
| 3 | Proposed STP | 4 |
| 4 | Existing RTDAS | 180 |
| Proposed RTDAS | 400 |
| 5 | Proposed SCADA | 20 |
| Existing SCADA | 2 |
| 6 | Existing Outlets | 18213 |
| Proposed Lining | 620 |
| 7 | Proposed CBMI | 120 |
| CBMI Works Executed Under NABARD | 98 |
| CBMI Works Executed Under State Plan | 32 |